Rehabilitation works on a 3668 metre section of the Kilmore-Lancefield Road at Lancefield are expected to start early this month and take about 12 weeks to complete, weather permitting.
Transport Victoria is undertaking the works to rebuild a section of road between Melbourne-Lancefield Road and Grahams Road to provide a stronger, smoother surface.
During works there will be lane closures and reduced speeds in place. Delays of 5-8 minutes should be expected.
Crews will be working from 7am to 6pm weekdays and Saturdays.
Heathcote-Kyneton Road, Langley
Rehabilitation works on a 2200 metres section of the Heathcote-Kyneton Road at Langley will also begin this month and take about 12 weeks to complete, weather permitting.
Works involve rebuilding a section of road from Diss Lane to Watts Lane to provide a stronger, smoother surface.
During works there will be lane closures and reduced speeds will be place. Delays of 5-8 minutes should be expected.
Crews will be working from 7am to 6pm weekdays, with the possibility of weekend works as required.
Maintenance program 2024-25
Rehabilitation works on the following roads will be undertaken between now and mid-2025:
Bendigo-Redesdale Road, between Wedge Gully Road and Sutton Grange Road, Redesdale (1.24km).
Kilmore-Lancefield Road, between between Melbourne-Lancefield Road and Grahams Road, Lancefield (3.48km).
Gisborne-Kilmore Road, between Mount Eliza Road and Melbourne-Lancefield Road (2.11km), and between Campbell Road and Pierce Road (1.24km).
Tylden-Woodend Road, near Chanters Lane (1.30km), and near Harpers Road (2.20km).
Heathcote-Kyneton Road, between Morgans Road and Perrys Lane, Redesdale (3km), and near Metcalfe Langley Road, Langley, (2.5km).