Contractors sought

The $17 million second stage will double the current indoor and outdoor offerings across the 15-hectare site.

An expansion of the Macedon Ranges Sports Precinct in New Gisborne is now out to tender, with designs progressed and contractors invited to submit their proposals.

The $17 million second stage will double the current indoor and outdoor offerings across the 15-hectare site either side of Barringo Road and north of Hamilton Road.

On the western sports hub site, proposed upgrades include three new multi-use indoor courts, four gender-neutral changerooms, additional car parking, a dedicated drop-off zone, additional offices and other public amenities.

On the eastern sports field site, proposed upgrades include a second natural turf oval to the north of the existing oval and pavilion, two outdoor netball courts, and additional car parking.

To help streamline the works, the second stage will be divided into two separate contracts: one focused on vertical construction such as buildings and the other focused on civil works such as ground works.

Contracts for the second stage are currently planned to be awarded to enable construction to start in late 2025, with works expected to be completed by late 2026.

While there will be an increase in construction activity and workers during this time, public-facing disruptions are expected to be minimal.

The sports precinct’s first stage was officially opened in June 2024 and delivered a three-court indoor sports hub, a natural turf oval with an adjoining sports pavilion and other facilities.

MRSC will continue its advocacy to secure funding for more upgrades to fully realise all elements outlined in the sports precinct’s master plan.